Fluidstack tools / 03 / Solar siting

Fastest States to install Solar

Compare six ISO/RTO regions by queue speed, completion rate, solar yield, permitting, and policy support. Adjust the matrix weight sliders based on current market conditions and the table sorts for the fastest States to install solar.

Matrix weights

2.0x
0x3x
1.5x
0x3x
1.2x
0x3x
1.0x
0x3x
1.0x
0x3x

ISO/RTO interconnection & NTP feasibility

6 regions / Baseline scenarios

Top-ranked region: ERCOT (Texas) · 80.3 / 100

ISO/RTO regions ranked by normalized NTP feasibility score
RankISO / RegionEst. months to NTPActive queue (GW)Completion rateSolar yield (kWh/m²/day)Feasibility score
01ERCOT (Texas)18 mos134 GW22%5.480.3 / 100
02SPP (Southwest)22 mos95 GW19%5.271.4 / 100
03MISO (Central)28 mos140 GW15%4.559.7 / 100
04CAISO (California)36 mos131 GW14%5.657.7 / 100
05NYISO (New York)32 mos45 GW12%3.954.2 / 100
06PJM (Mid-Atlantic)42 mos150 GW11%4.245.5 / 100

Oct 2026 · Supplied baseline · Not live

Model assumptions

The uploaded code attributes these fixed inputs to LBNL “Queued Up 2026,” EIA Form 860, and NREL NSRDB, but supplies no verified source records or working live feed. The October 2026 baseline label is supplied, not a verified update date. No live synchronization is performed.

These ISO/RTO scenarios are not individual state rankings or measured installation schedules. Estimated NTP months reuse the supplied average queue duration; actual notice-to-proceed depends on utility, site, permitting, and project-specific conditions.

Speed = max(1, 10 − queue months / 42 × 9). Completion = completion percentage / 25 × 10. Solar yield = daily irradiance / 6 × 10. The five weighted factors are divided by total weight × 10 and multiplied by 100; permitting and policy use the supplied ratings.